- Location Bridge St. Erskinville
- Client Water Delivery Alliance
- Contract Value $320,000
- Completion October 2008
[/vc_column_text][/vc_column][vc_column width=”8/12″][vc_column_text]Description of Work
– Construction of two bored piers and pile cap to support installation of 1800mmØ pipe
– Demolish & remove of part roof and walls of existing Sydney Water Building
– Remove existing cap from Sydney Water shaft, install 1800mmØ steel pipe elbow inside Sydney Water building onto existing shaft
– Install 1800mmØ butterfly valve on galvanised steel support
– Reinstall brick walls and roof above pipe
– Install steel frames and cladding around pipe